KMC/EEC/VII/59/2/26-27/R
Kolkata Municipal Corporation · Kolkata, West Bengal · Civil Works & Infrastructure · open
Key facts
- Tender value: ₹3.0L
- EMD: ₹6K
- Published: 31 Oct 2026
- Closing date: 13 Nov 2026
- Status: open
- Status as of: 04 Nov 2026 04:02 UTC
- Department: Executive Engineer (Civil), Borough VII
- Office: Executive Engineer (Civil), Borough VII, 9/1A AJC Bose Road
Description
Repairing passages at Loknath Bose Garden Lane, Tiljala Road, Asgar Mistry Lane and Topsia Road South, disturbed due to CESC, in Ward No. 59. Work is to be completed within 60 days from the work order, with commencement within 5 days. Estimated value is ₹299,715. EMD is ₹6,000.
Eligibility & requirements
- Startup relaxation: No
- MSE relaxation: No
- Documents required: Trade professional license under Section 199/200 of the Kolkata Municipal Act, 1980, or statutory authority documentation, Declaration regarding municipal officer or servant's interest and relationship or connection with specified Corporation officials, Contract labour licence under the Contract Labour (Regulation and Abolition) Act, 1970 and West Bengal Contract Labour Rules, 1972, where necessary
New to these terms? Read how tender eligibility criteria work.
Commercial terms
- Bid type: Percentage
- Evaluation: Lowest or fairest quotation; the Corporation is not bound to accept the lowest tender
- Make in India (MII): No
- MSE preference: No
Line items (12)
- Earthwork in cutting to form road section in correct profile including removal of spoils not exceeding initial lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post works) (i) In ordinary soil — Qty: 48.727 M3
- BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( 3rd Corrigenda & addenda dated 04.06.2018) — Qty: 208.83 SQM
- SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 15 Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m. — Qty: 348.05 SQM
- BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 13. Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge — Qty: 48.727 M3
- BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 6. Dismantling artificial stone flooring upto 50 mm. thick by carefully chiselling without damaging the base and removing rubbish as directed within a lead of 75 m. a) In ground floor including roof. — Qty: 139.22 SQM
- BUILDING WORKS(P) SOLING, EDGING AND METALLING??(15)Labour for taking out old soling edging including removing debris. (a) Single flat soling — Qty: 139.22 %SQ
- BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 2. Labour for laying single brick flat soling including ramming and dressing bed to proper level and filling joints with powdered earth. — Qty: 139.22 SQM
- ORDINARY CEMENT CONCRETE ( MIX 1:2:4 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES — Qty: 22.62312 M3
- MATERIALS AND LABOUR 1. Building (B) Labour Rates Per Diem : 3)Mazdoor (Male). Note: (I)The above rates of labour are exclusive of 10% contractors profit and 1% Labour welfare cess which would be admissible to the Contractors, but contractual percentage will not be applicable. (II) The workersemployed on high rise building or any structure over 30 ft in height and also workers engaged in Tunnel shall be paid 20% extra wages. — Qty: 10 EA
- Raising cover and frame of Special Inspection Pit with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster (1:4) including finishing with neat cement after cutting the asphaltum pavement taking out and re-fixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. ( Ref :Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6) and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13)) — Qty: 3 EA
- Raising cover and frame of Catch Pit with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster (1:4) including finishing with neat cement after cutting the asphaltum pavement taking out and re-fixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. ( Ref :Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6) and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13)) — Qty: 4 EA
- CESS 1% — Qty: 1 Nos
2 tender document(s) available — sign up to download.
Related tenders
- UNDER FRAME (LS & LWS PP) — Civil Works & Infrastructure · Tamil Nadu
- Macdamization of road surface at syed Kamalud din Colony wanganpora Eid gah Near UPHC from h/o Ali Mohd upto h/o Nasir Khalel. — Civil Works & Infrastructure · Jammu and Kashmir · ₹15.0L
- Operation of supply valves for the distribution pipe line for piped scheme Babaichya and Narwar with associated works, under jurisdiction of sub division rural, District Rural Division Ajmer (Excluding GST) — Civil Works & Infrastructure · Rajasthan · ₹3.3L
- Construction of Mali Hut at Bimalnag Nursery under CAMPA CAT RATTLE for the year 2026 27 — Civil Works & Infrastructure · Jammu and Kashmir · ₹16.7L
- CONSTRUCTION OF TOILET BLOCK IN SANOUR CITY — Civil Works & Infrastructure · Punjab · ₹9.1L
- Repair of street and drainage in w.no.2 — Civil Works & Infrastructure · Punjab · ₹25.0L
- Repair and renovation of University Library Building at GADVASU, Ludhiana. — Civil Works & Infrastructure · Punjab · ₹9.5L
- P/F Interlocking Tiles St. Baba Jora EO Gurudwara Street Ward No.07 — Civil Works & Infrastructure · Punjab · ₹3.4L